Canada Atlantic Railway

Depot Harbor Grain Elevator

Structure
History
3 facts
DateStatementSourceStatus
1896-10-09A gang has been sent up the line to build the grain elevators. Two will be built, with a million bushel capacity, to be completed by the spring of 1897.
The item speaks of two elevators, each with capacity 'a million bushel' in total; only one Depot Harbor Grain Elevator entity exists. 'Parry Sound Harbour' in the Mercury is read as Depot Harbor at the maintainer's direction.
Huntsville Forester 1896-10-09(Transcribed by Colin J. Churcher in 'Local Railway...)
1896-10-27A gang of thirteen men were sent up the OA & PS on Saturday to Parry Sound to build the grain elevators at the Parry Sound Harbour. The company will build two large elevators, having a storing capacity of one million bushels of grain. The elevators will be completed by next spring.
As above.
Mercury 1896-10-27(Transcribed by Colin J. Churcher in 'Local Railway...)
1896-12-04The Parry Sound Railway company are erecting two large grain elevators at the Sound harbor to be in readiness for next year's business. They will have a capacity of fully one million bushels.
As above.
Almonte Gazette 1896-12-04(Transcribed by Colin J. Churcher in 'Local Railway...)